Customers in the following areas with PUD fiber will experience an overnight internet outage: Emerald Lake, Zephyr Lane, Roos Court, Mason Benson Rd, Mason Lake, Ballantrae Dr, Tenby Way, Tiree Pl, Muirkirk Rd, and Aycliffe Dr, and surrounding areas while the PUD transfers critical equipment starting on the evening of June 7th at 7:00 p.m. into the morning of June 8th 7:00 a.m.

South Island Drive

South Island Drive

Providing the best internet available throughout the South Island Drive and Howard Cove area!

Project Information is up to date as of 03/14/23.

The South Island Drive & Howard Cove Fiberhoods will construct a ready-to-connect open-access fiber optic network to serve the citizens that live in the surrounding area with unlimited, symmetrical, gigabit broadband. At the completion of this project, fiber distribution will be constructed along existing pole lines and available at the road. Customers will then be able to submit an application to get their home or business connected to the network so they can turn up world-class internet, HDTV, and voice services.

PROJECT PARTNERS/FUNDING

This project is made possible in partnership with PUD 3’s Fiberhood program and the Community Economic Revitalization Board (CERB). PUD 3 was awarded a grant and loan to construct this network in September 2018. PUD 3 intends to meet the requirements of the grant to have substantial completion of the fiber distribution network by May 2023.

MANY STEPS TO GETTING CONNECTED

We understand that you likely wish you were connected already. Extending fiber networks to rural, unserved areas like yours is a very difficult, costly, and time consuming endeavor. If it was easy, a private for-profit company would have done it already! There are many, many communities throughout Mason County that are in similar broadband-deserts, without access to adequate internet. PUD 3 staff has to tell many inquiring customers every day that we are not in a position to serve them right now. Thankfully, your community’s story is different! You have done your part to rally your neighbors and express interest in PUD 3’s Fiberhood program. Now, it’s our turn to do the heavy lifting. Don’t worry, PUD 3’s teams are experts in this process! Over 3,000 homes and businesses around Mason County, in some of the hardest to reach areas, are now connected to the fiber optic network. We are working through our long construction queues and turning up new neighborhoods every month or so.

 

Here's a quick overview of the 8 STEPS to a PUD 3 Fiber Connection.

  1. Pre-Construction Engineering – Engineers evaluate poles in the area and call for adjustments or replacements to make room for the fiber cables, OR if existing power service is underground, they create designs to install new conduit where it won’t interfere with existing utilities and make as little impact as possible to roadways.
  2. Make Ready Crew – Linemen replace or reframe the poles AND/OR they dig trenches for fiber conduit if the main electrical lines are to remain underground.
  3. Telecom Engineering – Engineers then design the maps and estimate the supplies and equipment needed. This is a very technical process to ensure there is enough fiber for each existing parcel, and room for growth as the neighborhood develops. This step also includes identifying a location and installing a fiber distribution hut and creating a safe pull-off for PUD 3 crews to work at the hut.
  4. Main Line Fiber Crew – A fiber crew then installs the main fiber-optic cables and the service terminals in the neighborhood. This is very often a contract crew that PUD 3 hires to perform this work. The required competitive bidding process takes additional time, but it ensures PUD 3 is in compliance with the law and that we get the best deal possible on behalf of our customers.
  5. Splicing Crew – Splicers must join the newly installed cables together with a high-tech fiber fusion machine. This is usually yet another sub-contracted group. Sometimes this phase can seem to take a long time because the work occurs in a box van and is less visible than the installation of new infrastructure such as poles, conduit, or fiber cable.
  6. Service Drop Designer – Once the network is constructed at the road, customers within the Fiberhood can apply to get connected! An engineer meets with the homeowner on site to plan the best path to the home and review requirements.
  7. Service Drop Install Crew – The installation crew extends a service line and attaches a fiber gateway to the exterior of the home.
  8. Pick a Provider – With PUD 3’s open access fiber network, a number of retail service providers can deliver unlimited, symmetrical, gigabit internet (1000/1000 Mbps), HDTV, and/or phone services to your home over the single fiber optic cable. Shop around to get the best deal! If you’re not happy with one, pick another and utilize the same fiber line installed by PUD 3.

SO, WHICH STEP ARE WE AT NOW?

The South Island Drive Fiberhood mainline construction has been completed!  As we review and process the network test results, our Mapping Team is performing the as-built documentation and posting the completed work in our mapping system.  Once complete, we will send out announcement letters to those within the Fiberhood to solicit applications for service.  Announcement letters should be expected in late April / early May 2023.

Here's a PDF of a letter that was sent to area homes in October 2022.

PROJECT LIMITATIONS – Private Roads with Underground Utilities

PUD 3’s goal is to connect as many customers as possible, as quickly and as safely as possible. This means that our primary goal is to get the fiber distribution network constructed along the main road. If you live off of private roads such as Trillium Lane and Heron Cove, your power is underground and we don’t have existing fiber conduit in your street. Therefore, once we complete the main distribution network, we will have to come together with the community to discuss options to bring the fiber to your homes. Don’t worry, fiber capacity has been reserved and dedicated for each parcel- we just need to establish a plan, create engineering designs, and then perform construction to get it to you. We know this delays the timeframe for you to get connected, but we need to build upon each phase to get all homes and businesses in the area connected.

southislanddrivefiberhoods.jpg

COVID IMPACTS

COVID-19 has brought additional challenges in forecasting and executing construction projects throughout the world.  PUD 3 is no exception to these impacts caused by COVID-19.  For example, the raw materials used to construct our fiber network ranging from fiber optic cable, distribution terminals, pole attachment hardware, splice enclosures, vaults, pedestals, conduit, and the electronic gateway components that we install at each premise have been impacted at the manufacturing and distribution levels.  We have been (and are currently) experiencing supply-chain delays impacting several of these items.  We are doing everything possible to secure these needed materials to keep construction moving forward.  For the latest information on the supply chain issues that we are experiencing, click here.

Additionally, labor resources have been impacted due to COVID-19.  This, unfortunately, has caused construction times to increase due to absenteeism when a person gets infected, or has been in close contact with someone who is infected.

Please understand that we are working though these challenges diligently to keep projects on track in the most efficient manner possible.

Expand All

What should residents in the area expect during active construction?

Customers should be prepared for construction activity, increased road traffic, possible lane closures, and noise. The PUD will be using a contractor for the project, so residents may notice work vehicles that do not have the familiar PUD logo on them. However, rest assured, PUD employees will be on-site overseeing the activities at each step of the way. We do ask residents to practice safe driving and social distancing around construction zones for worker safety. During construction, there may be a need to take short outages to ensure the line workers’ safety. If that is necessary, affected customers will be notified in advance.

Why isn't the PUD doing the work?

Since this is part of a grant the PUD was awarded to extend its fiber optic network to an underserved area, the PUD must use a contractor to fulfill the grant's requirements. The contractor who successfully won the bid is performing the work but all work is overseen by PUD personnel. 

When will I be connected to fiber internet?

Honestly, probably not as soon as you would like. This very large project will take time to design and construct, with many phases in several different neighborhoods throughout your area. Once we have the designs completed, we will install conduit at the road; then bring it to your home; then install the fiber optic cable in it and splice every strand together; then test each strand throughout the whole network; then install the gateway at your home. Describing it is the easy part. As you’ll see, it will take many skilled craftsmen many dedicated, hardworking hours to get this lasting, future-proof network built. You can see a high-level overview of the process here.

How much will internet cost and how fast will it be?

We see Fiberhood customers getting unlimited, symmetrical, uncapped internet at 1000/1000 Mbps for about $85/month. HDTV and phone services are additional. However, PUD 3’s fiber network is unique. It is an “open access” network, which means that you, as the end user, can select from a number of different retail internet service providers and their packages. These providers deliver the service over the single PUD 3 fiber optic cable and they bill you directly. If you want to switch, it’s easy- and you don’t need a new connection to your home.

Why do I still have to pay the Fiberhood Application Fee and Construction Adder if you got a grant to build the network?

The CERB grant and loan covered a significant portion of the network construction and allowed us to consider the your area for fiber expansion, but it does not cover all of the expenses. The Fiberhood costs cover the remainder as well as a portion of the operating costs of the network into the future.

What if I don’t want to get connected now, but I may want to hook up sometime later?

You don’t have to get connected now. We will dedicate fibers to each parcel at the road. However, if/when you change your mind, you will be added to the queue and have to wait your turn. Sometimes that can be months. It’s best to submit your application for fiber connection as soon as we announce it is available. Only customers who are connected to the network and actively taking services pay the Fiberhood Construction Adder.

Will there be any additional costs to me other than the Fiberhood Application Fee and the Construction Adder on my internet bill?

The Fiberhood program covers most scenarios. However, each property may have unique challenges that we may not be able to accommodate. A customer may need to provide trenching and restoration for a portion on their private property; or a conduit pathway under a landscaped area, driveway, or sidewalk; or perhaps may need to permit the use of an aerial installation. Our engineering team are well versed in identifying great solutions to get homes connected to fiber and to help customers find a path that works for them.

What’s a Fiberhood?

Fiberhoods are the bedrock of PUD 3’s fiber expansion program. You can learn more about Fiberhoods here: www.pud3.org/fiberhoods. Your area does not need to sign up to reach the 75% goal; you’re already under construction!

Banner 3