Three Fingers Fiber Project

Providing the best internet available throughout the Three Fingers area!

Information Update as of May 2024

Three Fingers RoadAbout the Project

Over 250 customers in the Three Fingers area will have access to some of the fastest internet in the world. Going from dial-up like speeds of approximately 1.5 Mbps to unlimited, symmetrical, 1000 Mbps dedicated fiber connections on PUD 3’s open access network will revolutionize communications and increase opportunities for residents. This project was will be completed through the USDA RUS ReConnect Program, in partnership with PUD 3’s Fiberhood Program.

Project Timeline

In early 2020, PUD 3 was awarded a federal ReConnect grant to assist in construction of the Three Fingers fiber optic network. While we did experience some delays due to COVID and federal processes, we are now moving forward with this exciting but massive project. There are many phases to a project this size and we plan to keep you updated as we move along.

Project timeline steps: Engineering > Construction > Connection

Our engineering designers have completed the construction designs for this project!  The construction phase is underway in the Fox Run Lane, Leffler Loop, Wilson Way, Stadium Beach West, and Stadium Beach East areas.  In the months to come, they will progress to Stadium Beach West and Stadium Beach East.  Our crews are installing the underground conduit and vaults needed throughout the each Fiberhood zone prior to contracting out the installation, splicing, and testing of the fiber optic cable itself.

It will take a lot of time to complete construction to your area, but the final deadline to full project completion is April of 2026.  However, we anticipate we will be complete sooner than that.

8 Steps to a PUD 3 Fiber Connection


Here is a quick overview of the 8 Steps to a PUD 3 Fiber Connection.

  1. Pre-Construction Engineering – Engineers create designs to upgrade poles where needed to make-ready for the installation of new fiber facilities.
  2. Make Ready Crew – Linemen and PUD 3 crews replace and install poles where needed to provide an overhead path for the new fiber optic cables.
  3. Telecom Engineering – During the Pre-Construction Engineering, a Telecom Designer designs the construction maps and estimates the supplies and equipment needed. This is a very technical process to ensure there is enough fiber for each existing parcel, and room for growth as the neighborhood develops. This step also includes identifying a location and installing a fiber distribution hut and creating a safe pull-off for PUD 3 crews to work at the hut.
  4. Main Line Fiber Crew – An internal fiber crew then installs the main fiber-optic cables and the service terminals in the neighborhood.
  5. Splicing Crew – Splicers must join the newly installed cables together with a high-tech fiber fusion machine. This work will be performed by a contracted group. Sometimes this phase can seem to take a long time because the work occurs in a box van and is less visible than the installation of new infrastructure such as poles or fiber cable.
  6. Service Drop Designer – Once the mainline construction and splicing are complete, we will solicit service applications from those within the Fiberhood. A PUD 3 designer will work with each property owner to plan the best path to the home and review requirements prior to connection to the network.
  7. Fiber Gateway Install Crew – The PUD 3 installation crew completes the install of the service line and attaches a fiber gateway to the exterior of the home.
  8. Pick a Provider – With PUD 3’s open access fiber network, a number of retail service providers can deliver unlimited, symmetrical, gigabit internet (1000/1000 Mbps), HDTV, and/or phone services to your home over the single fiber optic cable. Shop around to get the best deal! If you’re not happy with one, pick another and utilize the same fiber line installed by PUD 3.

Three Fingers Project area mapWhat We Need From Area Residents

To speed up the timeline and help our engineers plan ahead for the scope of the project, we are asking residents in the project footprint to let us know if they would like to be placed on the construction list for connection to Mason PUD 3’s gig-speed fiber optic network. Eligible properties received a letter and application in August 2021. If you are within the project area and you need another application, please email our Fiberhood mailbox. A follow-up letter was sent to customers in February 2022 and phone calls were made to those that didn’t respond to ensure all interested parties let us know they want to get connected as soon as possible.

This application will notify the engineers that you want to be included in the construction phase. They will schedule a site survey with you at your home and design a plan to install conduit for the fiber cable. Even if you are not planning to get connected right away, it is very important to submit your application now so that we can prepare the path for future fiber while our construction crews are in the area.

Note: The Fiberhood application fee of $250 will not be billed until the connection phase of the project when it is time to install the fiber optic gateway on your home.

In Your Neighborhood

You will likely see PUD 3’s engineers, Stan and Cody, in your area over the next several years. There may be new paint markings on the ground which identify underground utilities and perhaps small wooden stakes. These aid in the design and safe construction of the fiber optic network. As we transition from design to construction, we appreciate your patience and potential traffic delays while our crews perform their work. Thank you for helping us to make safety a top priority.

Stan Cody

More About PUD 3 Fiber

It sounds like a lot, but don’t worry, PUD 3’s teams are experts in this process! Over 3,000 homes and businesses around Mason County, in some of the hardest to reach areas, are now connected to the fiber optic network. When complete, you will be able to select from a handful of local internet providers to get symmetrical, unlimited gigabit (1000/1000 Mbps) internet; HDTV; and phone service over the single fiber optic connection from PUD 3.

Frequently Asked Questions

What should residents in the area expect when construction begins?

Customers should be prepared for construction activity, increased road traffic, possible lane closures, and noise. PUD 3 will be installing new conduits underground to extend the fiber optic network to the area. The PUD will also be using a contractor for a portion of the project, so residents may notice work vehicles that do not have the familiar PUD logo on them. However, rest assured, PUD employees will be on-site overseeing the activities at each step of the way. We do ask residents to practice safe driving and social distancing around construction zones for worker safety.

During construction, there may be a need to take short outages to ensure the line workers’ safety. If that is necessary, affected customers will be notified in advance.

How long will the project take?

PUD 3 was given the green light to begin engineering designs in Spring 2021. We anticipate the total project to take up to 5 years (April 2026), but we plan to be able to connect homes in stages as we work through the area.

 

When will I be connected to fiber internet?

Honestly, probably not as soon as you would like. This very large project will take time to design and construct, with many phases in several different neighborhoods throughout your area. Once we have the designs completed, we will install conduit at the road; then bring it to your home; then install the fiber optic cable in it and splice every strand together; then test each strand throughout the whole network; then install the gateway at your home. Describing it is the easy part. As you’ll see over the next few years, it will take many skilled craftsmen many dedicated, hardworking hours to get this lasting, future-proof network built. We must have the project completed in full by April 2026, but we will go neighborhood-by-neighborhood while we work towards that goal.

 

Why did it take so long (January 29, 2020 announcement) to start work on this project?

That’s a good question. COVID brought many of its own challenges and delays- some of which we are only starting to feel now (e.g. supply chain issues). The ReConnect program - and the ability for PUDs in Washington State to participate - was a “pilot project” through the USDA Rural Utility Services (RUS). This caused significant delays on their end, which impacted their ability to give PUD 3 the green light to get started. There were also Archaeological and Environmental Surveys and Notifications that had to be completed. We wish we could have gotten started sooner- but we’re on it now!

How much will internet cost and how fast will it be?

We see Fiberhood customers getting unlimited, symmetrical, uncapped internet at 1000/1000 Mbps for about $85 per month. HDTV and phone services are additional. However, PUD 3’s fiber network is unique. It is an “open access” network, which means that you, as the end user, can select from a number of different retail internet service providers and their packages. These providers deliver the service over the single PUD 3 fiber optic cable and they bill you directly. If you want to switch, it’s easy - and you don’t need a new connection to your home.

 

What if I don’t want to get connected now, but I may want to hook up sometime later?

You don’t have to get connected now. We will dedicate fibers to each parcel at the road. However, if and/or when you change your mind, you will be added to the queue and have to wait your turn. Sometimes that can be months. Our strong recommendation is to submit the Fiberhood application now. We will design and install a conduit path to your home so that it will be an expedited connection when you’re ready to get hooked up in the future. Only customers who are connected to the network and actively taking services pay the Fiberhood Construction Adder.

Will there be any additional costs to me other than the Fiberhood Application Fee and the Construction Adder on my internet bill?

The Fiberhood program, in partnership with the ReConnect grant, cover most scenarios. However, each property may have unique challenges that we may not be able to accommodate. A customer may need to provide a conduit pathway under a landscaped area, driveway, or sidewalk; or perhaps may need to permit the use of an aerial installation. Our engineering team are well versed in identifying great solutions to get homes connected to fiber and to help customers find a path that works for them.

 

Why isn’t the PUD doing all of the work?

Since this is part of a grant the PUD was awarded to extend its fiber optic network to an underserved area, the PUD must use a contractor to fulfill a portion of the grant's requirements. All work is overseen by PUD personnel.

Who is eligible to get connected? Where will the fiber network be built?

Three Fingers Project area mapHomes and businesses within the project area, which is primarily along Leffler Loop, Wilson Way, Stadium Beach West, Stadium Beach East, Robbins Road, Columbine Lane, Sublimity Lane, Orchid Lane, Green Way, Ruby Road, Stadium Beach East, Stadium Place, Stadium Lane, Fox Run Lane, Wild Grape Way, and connecting and nearby roads.